Itekeng High Mast Light Project

The project entails the installation of six high Mast Lights at Itekeng

Status: 
Completed
Contractor: 
JV PFP CONTRACTORS AND COCO HAVEN 1046 CC
Location: 
Itekeng
Dates: 
November-2010
Value: 
R 1,600,000
Update: 

 

The contractor was on site since June 2009 and currently the following has been achieved:

  • Excavations and concrete for all the high mast lights footing completed to date.
  • 12 people employed on the project.
  • High Mast Light Structures was installed during November 2009 however, only four lights are connected and the remaining two lights are waiting for Eskom connection points.
  • Eskom indicated that the two outstanding high mast lights will be connected during October 2010.